Marienloher Straße - WWN will lay power line from March 4th
From Monday, March 4th, Westfalen Weser Netz GmbH will re-lay the power line on Marienloherstraße. For this purpose, Marienloher Straße will be closed on one side for around 100 meters from the Schloßstraße roundabout.
The work is being carried out using the open construction method and is expected to last until March 22nd in this first construction phase.
The second construction phase will then start, probably from March 25th. Here, Schloßstrasse will be closed on one side from the roundabout for around 100 meters in the direction of Paderborn. A new power line is also being laid here using an open construction method.
The second construction phase is scheduled to be completed by May 3rd.
Bekeweg and Sommerau - Work WWN from February 26th
Initiator of the measure: Westfalen Weser Netz
Location: Marienloh, Bekeweg & Sommerau
Reason for the work: re-laying of the water, electricity and gas pipes
Construction: Open construction with half-side closure
Start of the measure: February 26, 2024
Duration of the measure: Until around the end of June
Stemberg in Wewer - work by WWN from March 11th
Initiator of the measure: Westfalen Weser Netz
Ort: Wewer, Stemberg
Reason for the work: re-laying of the water, electricity and gas pipes
Construction method: Open construction with full closure
Start of the measure: March 11, 2024
Duration of the measure: Until around the end of May